Installation Preparation Checklist
Everything an installer should confirm before the pack arrives — location, structure, cabling, protection and commissioning information.
Most installation call-outs are decided before the technician arrives: a wall that cannot carry the weight, a cable that is one size too small, or a commissioning form nobody filled in. Work through this list at survey stage.
Location and structure
| Check | Target | Why it matters |
|---|---|---|
| Ambient temperature | 0 – 40 °C, shaded | Charging below 0 °C is blocked by the BMS; above 40 °C accelerates ageing |
| Enclosure | Indoor or IP54 cabinet; no direct rain | Terminals and comms ports are not weatherproof |
| Wall / floor strength | ≥ 2× pack weight | A 16 kWh pack with bracket is roughly 160 kg |
| Clearance | 150 mm sides, 300 mm top | Heat dissipation and service access |
| Distance to inverter | ≤ 2 m DC run | Voltage drop and cable cost |
Electrical
| Item | Specification | Note |
|---|---|---|
| DC breaker | 1.25 × continuous current, 125–250 A | DC-rated, not an AC MCB |
| Cable | 35 mm² up to 3 m at 100 A; 50 mm² above | Both poles fused or breaker-protected |
| Grounding | Pack earth to installation earth bar | Continuity tested before energising |
| BMS comms cable | Shielded, pin-out per inverter model | One end of shield grounded only |
| Surge protection | Type 2 AC SPD on the inverter output | Lightning-prone regions |
Documentation to hand over
- Single-line diagram showing battery, breaker, inverter and earthing.
- Load list with measured standby and peak current.
- Commissioning sheet: firmware version, protocol selected, absorption and cut-off values, first full-charge date.
- Serial numbers of every pack, photographed on the label.
First power-on sequence
- Measure pack voltage at the terminals — a healthy 51.2 V pack reads 52–53 V at 50 % state of charge.
- Check polarity and torque (typically 8–10 N·m on M6 terminals).
- Close the DC breaker, then start the inverter and confirm the BMS shows current in the expected direction.
- Run one full charge to 100 % so the BMS learns the top of the curve; state-of-charge readings are unreliable before that.
If the site has no grid and the inverter is off-grid only, confirm the inverter can start from the battery without PV. Some hybrid models need PV or grid to boot and will not black-start from a pack.